Summit High crossing signal would cost Fontana and its school district $1.06 million under proposed split
Fontana and the Fontana Unified School District would split the estimated $1,057,400 cost of a pedestrian signal on Summit Avenue near Summit High School under an agreement before the City Council Nov. 24.

What to know
- Fontana and its school district would split an estimated $1,057,400 pedestrian signal on Summit Avenue near Summit High School.
- Each agency would pay about $528,700, and the city would maintain the signal after it is built.
- The council votes Nov. 24; if approved, the city owes the district a project schedule by March 1, 2027.
People crossing Summit Avenue near Summit High School in Fontana would get a new traffic signal built for pedestrians under a proposed deal between the city and the Fontana Unified School District. The two agencies would split the estimated $1,057,400 cost evenly.
The Fontana City Council is scheduled to vote on the agreement Nov. 24. The signal would go on Summit Avenue near Parkhouse Drive, next to the high school campus.
For students, families, and neighbors who walk in the area, the deal is the first formal step toward a signal where none exists now. The agreement says the goal is safer pedestrian crossings near the school.
For taxpayers, each agency would cover about $528,700, or half of the cost estimate. The city would also take on the job of running and maintaining the signal after it is built, with no end date listed.
Who does what
The city would lead the project from start to finish, according to the agreement. That includes hiring engineers, designing the signal, working with utility companies on lines in the way, getting permits, and managing construction.
The city would also handle any review required under the California Environmental Quality Act, the state law that requires agencies to study a project's effects on the environment. The agreement says that review would happen only if it applies.
The school district's role is mostly to review and coordinate. It would get 20 business days to comment in writing on plans, cost estimates, and other work. If the district does not respond in time, the city may treat the plans as approved and keep moving.
The district would also share school schedules, events, and drop-off and pick-up times. The city agrees to make reasonable efforts to schedule construction so it disrupts the school as little as possible.
What it costs and what could change
The agreement treats the $1,057,400 figure as an estimate. The two agencies would split engineering, utility work, construction, construction engineering, and any contingency costs actually spent.
If construction bids come in up to 25% over the estimate, the city could still award the contract without going back for new approvals. Both agencies' shares would rise to match. At the 25% limit, the total would reach about $1.32 million, based on the estimate in the agreement.
If bids come in more than 25% over, the city could not award a contract. The agencies would then have 30 days to agree in writing on another path, such as bidding the work again. If they cannot agree, the deal would end.
The city would bill the district every month. The district would have 45 days to pay each bill.
The agreement does not say where the city's share of the money would come from. The agenda materials also do not include crash or injury figures for the crossing, or a target date for finishing the signal.
What comes next
The item is on the council's consent calendar, a list of routine items approved together in one vote without discussion unless a council member asks to pull one out. It is listed as item E, file 26-1322. The meeting starts at 2 p.m. at the Steelworkers' Auditorium, 8437 Sierra Avenue.
If the council approves, the city must give the district a proposed project schedule by March 1, 2027. The city would also hold monthly meetings with district staff to report on schedule, cost, and any changes in scope.
The agreement still needs a signing date, and the school district's governing board would need to approve any spending above the agreed budget. Residents can watch for the March schedule to learn when construction near the campus might begin.