Moonspinner Street intersection work in Chino would take 30 working days under a proposed $227,700 contract

Chino's City Council is scheduled to vote Dec. 1 on a $227,700 contract with Van Engineering Inc. for work at Moonspinner Street and West Preserve Loop, with 30 working days to finish.

From the Dec. 1 Chino City Council agenda packet
A dump truck unloads gravel into paving equipment as a crew works on a road in Hood River, Oregon.
A dump truck unloads gravel into paving equipment as a crew works on a road in Hood River, Oregon. File photo. Photo by Tom Shamberger on Pexels

What to know

  • Chino would pay Van Engineering Inc. $227,700 for work at Moonspinner Street and West Preserve Loop if the council approves.
  • The company would have 30 working days to finish and would owe penalties for delays, but the packet does not describe the work.
  • The council votes Dec. 1; the start date and any lane closures are not yet known.

Construction crews would rebuild parts of the intersection of Moonspinner Street and West Preserve Loop in Chino if the City Council approves a $227,700 contract with Van Engineering Inc. on Dec. 1.

The proposed deal gives the company 30 working days to finish once the city tells it to start. If the job runs late, the contract lets the city charge the company a penalty.

For people who drive, walk, or bike through that corner, the vote decides who does the work, what it costs, and how long it lasts. The city calls the job "Intersection Improvements" and labels it project TR271.

What the record leaves out

The agenda packet contains only the contract. It does not describe the work itself. It does not say whether the project adds signals, crosswalks, turn lanes, ramps, or something else, or why the city picked this intersection.

The packet also does not say how many companies bid or where the money comes from. It does not say whether the city set aside extra money for surprises. It gives no start date and does not say whether lanes would close while crews work.

What it costs and who carries the risk

The contract sets the price at $227,700, the amount in the company's bid. That total can go up or down. Change orders can alter it. These are written changes to the work and price during construction. Formal amendments can also change it, and so can penalties charged to the company.

Under the agreement, Van Engineering would supply all workers, tools, equipment, and materials, unless the plans say the city provides certain items. The company would also cover losses from weather or unexpected problems until the city accepts the finished work.

The penalty for delays is called liquidated damages. That is a set amount the contractor agrees ahead of time to pay for each late day, so the city does not have to prove its actual losses. The contract says these penalties apply but does not list the daily amount. It points instead to the bid documents, which are not in the packet.

According to the agreement, the company would also have to defend the city if someone files a claim tied to the contractor's negligence or failure to meet the contract. It would pay the city's costs too. That protection does not cover harm the city alone causes. Where the city shares the blame, the company would pay only its own part.

Conflict rules and signatures

The contract bars any city officer or employee from holding a financial stake in the deal. The company must also promise it paid no one to win the contract. Any lawsuit over the agreement would be filed in San Bernardino County.

Hye Jin Lee, the city's director of public works, signed off on the contract's content. If the council approves, City Manager Linda Reich would sign for Chino and City Clerk Natalie Gonzaga would attest. The company's signature must be notarized.

What comes next

The council meets at 6 p.m. Tuesday, Dec. 1, in the council chambers at City Hall, 13220 Central Ave. The contract is item 9, listed under new business. Residents can comment on agenda items at the meeting.

If the council approves the deal, the 30-working-day clock starts only when the city issues its formal notice to start work. The record does not say when that would happen. Residents near the intersection may want to watch for a start date, any lane closures, and any change orders that raise the final cost.

Stories bylined Gazette Staff are produced by the IE Gazette newsroom from public records: agenda packets, staff reports, minutes, filings and budgets. Each one links to the documents it was drawn from.

Drafted with automated tools from public records and checked against those records before publishing.