Redoing earlier freeway plans would push Murrieta's Keller Road design contract to $2.9 million, if approved
Murrieta's design contract for a Keller Road interchange at I-215 would grow to $2.9 million and run to mid-2029 if the council approves. The firm says earlier plans needed major revisions to meet Caltrans standards.

What to know
- Murrieta's Keller Road interchange design contract would be capped at $2,931,606.59 and extended to June 30, 2029, if the council approves.
- The firm says earlier plans fell short of Caltrans expectations, and the project schedule grew from 8 months to 23 months.
- The council votes Dec. 1 on its consent calendar. The interchange still had $21.4 million unfunded as of October.
Murrieta's design firm for a new Keller Road interchange at Interstate 215 would get a larger contract and an extra year under a change on the City Council's Dec. 1 agenda. The deal with Mark Thomas & Company would be capped at $2,931,606.59 and run through June 30, 2029.
The firm says the extra money covers work it did not expect to do. Its contract assumed the project's earlier designs were about 65% complete and had already been reviewed by Caltrans, the state transportation agency. Once work began, the firm says, it became clear those plans did not meet Caltrans expectations and needed major revisions.
The interchange is one of the city's costliest unfinished projects. In October, a staff analysis put it at $63.25 million, with $21.4 million unfunded. That was the largest gap on the city's list of top-priority projects, and the council declined to borrow through bonds to close that gap.
What changed
The city signed the original contract on Sept. 3, 2025. The firm was hired to finish construction-ready drawings, specifications, and cost estimates for the design the city had chosen, called Alternative 5. The firm was also hired to map the land the project needs and help during construction.
The amendment documents provided do not state the original contract amount. So they do not show exactly how much the cap would rise.
In a Nov. 9 letter to Public Works Director Bob Moehling, the firm said it has already done much of the added work. It did so at the city's direction by moving money among tasks within the existing budget. The firm wrote that the original budget now cannot cover the work through the end of design.
The letter lists 10 areas of added work. Among them:
The project schedule grew from 8 months to 23 months, the letter says. That required weekly and as-needed meetings with Caltrans, utilities, and others, rather than the monthly meetings first planned.
Earlier property survey work was not detailed enough for the state's standards on buying land, the firm says. It added field work to find and confirm survey markers and property lines.
Utility companies had to be contacted again because the design changed and time had passed. The firm says earlier utility work had been based on another firm's design, Jacobs.
The revised road layout changed which land the city needs. The original scope called for 26 legal descriptions and maps of property pieces. The firm says 26 more are now needed, partly for temporary construction easements, which give a project short-term use of private land.
Other added tasks include extra traffic signal and electrical design and early bridge and retaining wall work requested by Caltrans. The firm also lists environmental work, including a land swap under a county habitat conservation plan and a bumble bee survey. Support for agreements with Caltrans on the freeway and its upkeep is also included.
Why the timing matters
The firm says each added task was meant to protect key steps: Caltrans approval of the plans, readiness to buy land, and the target date to seek construction bids. The letter warns that skipping the work risked delays and land-buying disputes.
The documents do not say when construction would start or how the added design cost affects the project's overall $63.25 million estimate. They also do not say where the city would find the money for the larger contract.
In October, staff said top projects would return to the council for funding one at a time as they became ready. Staff also urged the council to consider moving less advanced or poorly funded projects to lower tiers.
What comes next
The contract change is item 15 on the consent calendar. That is a list of routine items approved together in one vote, without discussion, unless a council member asks to pull one for separate debate.
The council meets at 4 p.m. Tuesday, Dec. 1, in Council Chambers at 1 Town Square. If approved, the amendment takes effect when the city signs it. Next steps to watch are Caltrans approval of the revised plans and the city's offers to buy land along the route.