Fontana builders would get up to three more years to start projects under rules facing final vote

Fontana's City Council is set to give final approval Nov. 24 to rules letting project approvals be extended up to three years and requiring paved parking lots, driveways, and loading areas.

From the Nov. 24 Fontana City Council agenda and Ordinance No. 1998
Heavy equipment grades an unpaved lot beside a new industrial building.
Heavy equipment grades an unpaved lot beside a new industrial building. File photo. Photo by On Shot on Pexels

What to know

  • Fontana's council is scheduled to give final approval Nov. 24 to rules allowing extensions of up to three years for project approvals.
  • The rules would also require paved parking lots, driveways, and loading areas, and they would drop a Planning Commission review step.
  • If adopted, the rules take effect about Dec. 24 and would not apply to applications already deemed complete.

Fontana developers and business owners who already have city approval for a project would get more time to start building. The City Council is scheduled to give final approval to the rule changes on Nov. 24.

The package would let the city's planning director extend two kinds of approvals by up to three years. It would also require paving for every parking lot, driveway, drive aisle, and loading area. It would loosen several other city procedures too.

The extensions matter because city approvals expire if work does not begin. Under the current code, a design review approval lapses two years after it is granted. It stays valid only if the builder has pulled permits, started the main building, and passed a first city inspection. The ordinance, which is a city law, states that the changes aim to make development rules clearer and simpler while helping commercial projects and local businesses.

What would change

The first change covers design review, the city's check of a project's site layout and building appearance. It also covers conditional use permits, which give special permission for a business or use that a zone allows only under certain conditions. Under the ordinance, these approvals could be extended for no more than three years. The same goes for later amendments and modifications to them.

For design review, the planning director could grant an extension only if the approved site plan and building exteriors stay the same, according to the code language. A project that already received a two-year extension before the new rules could get one more year. That would bring its total extension to three years.

The second change affects who reviews smaller revisions to a project. Now, when the planning director signs off on an amendment or modification to a design review approval, the director must take it to the Planning Commission. The ordinance would remove that step.

The package also changes the rules for running a business from home. Anyone applying for a home occupation permit would need approval from the property's owners. For a manufactured home, approval would come from the owner of the residence. The ordinance's title describes this as extending the home business permit to cover manufactured homes.

The remaining changes are narrower. Sites and buildings that do not meet current rules in the city's Form-Based Code zoning district would get more options when they are remodeled or rebuilt. That district's zoning focuses on the shape of buildings and how they meet the street. The ordinance does not spell out the new options in the section provided.

The city would also redraw its Auto Center Overlay map to match a map it adopted earlier. It would clarify the required widths and depths of driveways as well.

How it got here

The Planning Commission reviewed the changes at a public meeting on Oct. 6 and recommended them to the council. The council held a public hearing on Nov. 10 and gave the ordinance its first approval. A city law needs a second, final vote before it can take effect. The agenda does not list how council members voted on Nov. 10.

The Nov. 10 meeting is the most recent Fontana City Council meeting with recorded actions in the Gazette's Votes Logged tracker. The tracker counts 36 recorded council actions across 13 meetings in 2026.

The city found that the changes are exempt from the California Environmental Quality Act. That state law requires a study of a project's effects on the environment. The city relied on the rule that exempts actions with no possibility of a significant effect.

The new rules would not apply to development applications the city's planning staff has deemed complete before the ordinance takes effect. Those projects could still be approved under the old rules. They would be allowed to stand even if they do not meet the new ones.

What comes next

The ordinance is on the consent calendar, a list of routine items the council approves together in one vote without discussion. Any council member can ask to pull an item for a separate vote. The meeting begins at 2 p.m. Nov. 24 at the Steelworkers' Auditorium, 8437 Sierra Avenue.

If the council adopts it, the ordinance would take effect 30 days later, around Dec. 24. The city clerk must publish it in the Fontana Herald News within 15 days of passage.

The record does not say how many existing approvals are close to expiring. It does not say how many projects could use the longer extensions. It also does not say how many current parking lots or driveways are unpaved.

Stories bylined Gazette Staff are produced by the IE Gazette newsroom from public records: agenda packets, staff reports, minutes, filings and budgets. Each one links to the documents it was drawn from.

Drafted with automated tools from public records and checked against those records before publishing.

More Logistics & Business

More
Every weekday, 6 a.m.

The Morning Gazette

The five stories that matter in the Inland Empire, the meetings happening tonight, and today's air quality. Free, in your inbox before the 91 backs up.

No spam. Unsubscribe any time.