Logistics & Business·Hesperia·Agenda preview

Planned Poplar Street warehouse in Hesperia would get until March 2028 if city panel grants extension

A Hesperia city panel will decide Dec. 2 whether to give a developer more time on a 414,700-square-foot distribution building planned for 20 acres along Poplar Street. The approval would last until March 2028.

From the Dec. 2 Hesperia Development Review Committee agenda and conditions of approval
A water tank painted with a 'Welcome to the City of Hesperia' message stands beyond dry desert scrub with mountains in the distance.
A water tank painted with a 'Welcome to the City of Hesperia' message stands beyond dry desert scrub with mountains in the distance. File photo. Carchiav / Wikimedia Commons (CC BY-SA 4.0)

What to know

  • A Hesperia panel will decide Dec. 2 on a second extension for a 414,700-square-foot distribution building on Poplar Street.
  • It would be among the largest warehouse projects on Inland Empire agendas this year, according to the Gazette's tracker.
  • If approved, the developer would have until March 21, 2028, to meet all conditions, or the approval becomes void.

A Hesperia city panel will decide Dec. 2 whether to give a developer more time on a large warehouse plan. If the panel agrees, the plan for a 414,700-square-foot distribution building on Poplar Street would stay alive until March 21, 2028. This would be a second extension of time.

The project would sit on 20 gross acres on the north side of Poplar Street, between Lassen Road and Mesa Linda Street. The applicant is Poplar 18, LLC, according to the agenda.

The extension does not approve a new building. It keeps an earlier approval from expiring. That approval is a conditional use permit. It lets a property owner run a certain use in a zone only if the owner meets a list of set conditions.

Why it matters

The building would be one of the larger warehouse projects to reach an Inland Empire agenda this year. The Gazette's Warehouse Watch tracker counts 16 warehouse, logistics and industrial projects placed on agendas in 2026 in eight jurisdictions. Ten of them list a building size. Only two are bigger than the Poplar Street plan.

One of those two is also in Hesperia. In July, the same Development Review Committee took up a request to shrink a distribution warehouse on 61.2 acres, from 1,108,000 to 1,045,895 square feet, the tracker shows. The tracker counts items placed on agendas, not approvals.

The Poplar Street project does not appear on the tracker's list. Its file number suggests it was opened before 2026. The tracker only counts files opened this year.

What the extension would require

Under the list of conditions attached to the item, the extension would take effect Dec. 15 and run until March 21, 2028. If the developer has not met every condition by then, the approval becomes void, the document states. The developer could ask for another extension. That would mean filing an application and paying a fee before that date.

The site is zoned for commercial, industrial and business park uses under the Main Street and Freeway Corridor Specific Plan. A specific plan is a detailed land-use plan for one area.

Many of the conditions deal with rain runoff. The project must show that storm water leaving the finished site will not exceed 90% of what flows off the land today during a major 100-year storm. Basins and drywells may not hold standing water for more than 48 hours. Drywells are underground pits that let water soak into the soil.

The developer would also have to submit a plan to keep construction pollution out of storm water. It would have to file a final drainage study as well. Any underground storage systems for runoff must be built from materials expected to last at least 50 years.

The conditions also require the developer to defend the city against any lawsuit that challenges the approval. The developer would pay for that defense. This includes claims under the California Environmental Quality Act. That is the state law that requires agencies to study a project's effects on the environment.

What the record does not say

The agenda materials do not say when the permit was first approved. They do not say when the first extension was granted. They also do not explain why the developer needs more time.

The packet does not estimate truck trips, jobs, or tax revenue from the building. It also does not describe who would use it. The conditions list shows whether each requirement has been met. In the pages included in the packet, only one item is marked as done. That item is sending construction plans to the city's building division.

What comes next

The Development Review Committee is scheduled to take up the request at 10 a.m. Wednesday, Dec. 2, in the Joshua Conference Room at Hesperia City Hall. It is the first item on the agenda.

If the panel approves the extension, the developer would have until March 2028 to clear the remaining drainage, engineering and permit conditions before work could begin. The conditions list notes that the developer could still ask for a further extension before that deadline.

Stories bylined Gazette Staff are produced by the IE Gazette newsroom from public records: agenda packets, staff reports, minutes, filings and budgets. Each one links to the documents it was drawn from.

Drafted with automated tools from public records and checked against those records before publishing.

More Logistics & Business

More
Every weekday, 6 a.m.

The Morning Gazette

The five stories that matter in the Inland Empire, the meetings happening tonight, and today's air quality. Free, in your inbox before the 91 backs up.

No spam. Unsubscribe any time.