Friday, Nov. 27, 2026The AgendaAQI 79 Moderate
IE Gazette
Independent news for Riverside and San Bernardino counties · Est. 2026
Riverside County·Riverside·Agenda preview

Proposed $3.1 million Bobby Bonds Park pool repair would leave Riverside's infrastructure reserve under $1 million

Riverside's council votes Dec. 1 on a $3.1 million plan to resurface and repair the 1959 Sippy Woodhead Pool at Bobby Bonds Park. The plan would drain the city's infrastructure reserve to under $1 million.

From the Dec. 1 Riverside City Council agenda packet and staff report
Clear blue water and marked swim lanes fill an outdoor swimming pool, with a tiled deck edge and drain grate in the foreground.
Clear blue water and marked swim lanes fill an outdoor swimming pool, with a tiled deck edge and drain grate in the foreground. File photo. Photo by Jan van der Wolf on Pexels

What to know

  • Riverside's council votes Dec. 1 on a $3.1 million contract to resurface and repair the Bobby Bonds Park pool.
  • The 1959 pool has never had major resurfacing on record, and the plan would cut a city reserve below $1 million.
  • Bid prices expire Dec. 11, and the bulkhead work depends on federal grant money the city has not yet received.

Riverside's only city-run 50-meter pool would get a new surface, new heaters, and a partly rebuilt deck under a $3.1 million plan the City Council is scheduled to vote on Dec. 1. The Sippy Woodhead Pool at Bobby Bonds Park opened in 1959. City records show no major resurfacing since then, according to a parks staff report.

The pool hosts city swim lessons, a summer splash day camp, free swim days, and open swimming for all ages. The Riverside Aquatics Association, a youth swim club, also trains there. It is one of five heated pools the city runs for public use, the report says.

To pay for the work, the council would pull $1.2 million from the city's infrastructure reserve. That would leave the reserve with less than $1 million for other city needs, staff wrote.

Why the pool needs work

The pool deck and the slab beneath it have large cracks, and concrete is failing at the gutter, the report says. Industry guidance calls for resurfacing a pool every eight to 10 years. This pool's surface has gone more than six decades.

Cracks in a pool's surface can leak and can hold bacteria, fungi, and dirt that may harm swimmers' health, staff wrote. The work is meant to make the pool last longer, cut upkeep costs, and improve safety.

The contract covers five pieces of work. The biggest is resurfacing the pool, at $1,199,044. Replacing one section of the deck and its equipment would cost $998,000. New pool heaters would cost $354,960, and new valves in the equipment room would cost $36,720.

The fifth piece is a new bulkhead, at $348,840. A bulkhead is a movable wall that splits the pool in two so different programs can run at once. The project also adds lifeguard chairs and a lift to help people who use wheelchairs get in and out of the water.

What it costs and who pays

The council would hire Ultimate Pool Remodeling, Inc. of Riverside for $2,937,564. Another $158,436 would cover unexpected changes, permits, testing, and inspections. That brings the total to $3,096,000.

The money would come from four places, according to the report. Grant and restricted funds already set aside for the pool would cover $500,000. The infrastructure reserve, part of the general fund, the city's main budget for day-to-day services, would supply $1.2 million.

Another $1 million would move from a Measure Z account for overdue park repairs. Voters approved Measure Z, a one-cent sales tax, in 2016 to help pay for city services and building repairs. The same Measure Z capital money is also paying for the Museum of Riverside expansion architect.

The last $396,000 would be federal Community Development Block Grant money, which the U.S. Department of Housing and Urban Development gives cities for community projects. The city has not yet received its grant agreement for this budget year. The bulkhead work depends on that money, the report says. If it does not arrive, the bulkhead would be dropped from the contract, and the city would look for other funding later.

Staff does not expect the work to raise the pool's operating or maintenance costs.

A second try at bidding

The city first sought bids for the pool work in spring 2025. It rejected all of them because it lacked the money, the report says. Staff then split the job into a smaller core project with optional add-ons, so the city could buy pieces as funding allowed.

The city received three bids this time. The lowest core price, $890,000, came from Elegant Construction, Inc. of Irvine. Staff recommends rejecting that bid because, according to the report, the company did not provide required notarized signatures on two bid documents.

Ultimate Pool Remodeling's core price was $998,000, just under the engineer's $1 million estimate. California Commercial Pools, Inc. of Glendora bid $1,196,000.

Even with the new money, one add-on is left out. Replacing a second section of the deck, priced at $98,710, would not be funded, the report says.

What comes next

The council meets at 1 p.m. Dec. 1 in the Art Pick Council Chamber at City Hall, 3900 Main St. The meeting is also streamed online. The pool contract is item 30. Moving money out of the reserve takes at least five council votes.

The bid prices hold only through Dec. 11, according to the bid award form. The report does not give a construction schedule or say whether, or for how long, the pool would close during the work. The bulkhead's fate still depends on the federal grant agreement arriving.

Stories bylined Gazette Staff are produced by the IE Gazette newsroom from public records: agenda packets, staff reports, minutes, filings and budgets. Each one links to the documents it was drawn from.

Drafted with automated tools from public records and checked against those records before publishing.

More Riverside County

More
Every weekday, 6 a.m.

The Morning Gazette

The five stories that matter in the Inland Empire, the meetings happening tonight, and today's air quality. Free, in your inbox before the 91 backs up.

No spam. Unsubscribe any time.