Bloomington warehouse park would pay Rialto $765,177 for sewer hookup under proposed deal
The Bloomington Business Park's owner would pay Rialto an estimated $765,177 to hook up to city sewers, then 1.3 times city rates, under a proposed deal. A Rialto commission is scheduled to consider it Nov. 17.

What to know
- Rialto would extend sewer service to the Bloomington Business Park, which lies outside city limits and has no other sewer system.
- The owner would pay an estimated $765,177 up front, build a pump station and pipelines, and pay 1.3 times city rates.
- The commission's vote is only a recommendation, and the City Council and a county boundary panel must approve the deal.
The owner of the Bloomington Business Park, a warehouse project outside Rialto's city limits, would pay an estimated $765,177 to hook up to Rialto's sewer system under a proposed agreement. After that, it would pay monthly sewer bills at 1.3 times city rates. Rialto's Cable Advisory and Utilities Commission is scheduled to consider the deal Tuesday, Nov. 17.
San Bernardino County supervisors reapproved the park's three warehouses in September after a court ordered a new environmental review. The property sits outside Rialto's boundaries but inside its sphere of influence, an area the city may someday annex, or add to the city. No other sewer system serves it, according to the draft agreement and the staff report. Rialto's system already serves some parts of Bloomington, staff wrote.
The commission's vote would be a recommendation only. The City Council, also acting as the Rialto Utility Authority, would make the final decision. The deal would take effect only if the Local Agency Formation Commission for San Bernardino County approves it. That county panel oversees changes to city boundaries and services. The draft says state law lets a city extend services into its sphere of influence only with that panel's approval.
What the developer would build and pay
The agenda names the owner as IV5 Bloomington Gateway Distribution Center II LLC, while the draft agreement leaves out the "II." Sewer service comes from Rialto Water Services, which holds the city's utility concession, a contract giving it the right to provide the service. Veolia operates the system, the document states.
The owner would get one connection near Santa Ana and Maple avenues.
To reach it, the owner would design and build a sewer lift station, which pumps wastewater uphill. It would also build about 5,945 feet of gravity sewer line, where wastewater flows downhill. It would add 2,339 feet of force main, a pipe under pressure, plus smaller side pipes called laterals. The owner would pay for all of it and not be paid back, according to the agreement and the Public Works staff report.
The Maple Avenue Lift Station would come with conditions. The city would get easements, or legal rights, to reach and maintain it. The station would need a permanent backup generator and four to six hours of backup power for its communication and control systems.
The lift station must be finished before the property can get a certificate of occupancy, the official sign-off that a building is ready to use.
Once the city accepts the new pipes and station, it would take over running, maintaining, repairing and replacing them. The owner would stay responsible for the laterals and the connection point in the right-of-way, the public strip of land along the street.
The one-time fee is made up of $727,737 for treatment and $37,440 for collection, the staff report says. It reflects the 1.3-times surcharge, or extra charge, that Rialto set in 2013 for sewer customers outside the city.
Rialto Water Services would send the bills. The utility authority would absorb the cost of serving the property under its concession agreement, the report says.
Beyond those fees and its building costs, the owner would not pay the city's costs to move, treat and dispose of the wastewater. Staff concluded the deal is not a project under state environmental law because the system has enough capacity.
The city could cut off service only if the owner's failure to meet the deal posed an immediate threat to public health or safety. Even then, the city would have to give written notice and at least 30 days to fix it, except in emergencies.
If a change in use pushed sewer demand above the amount the city approved, the owner would need the city's consent. The city could not unreasonably refuse it.
The agreement would have no end date. It would end only if one side ended it or the property became part of Rialto. At that point, the owner would pay regular city rates. The city could end the deal only for a serious breach that went unfixed, or if the law required it.
What comes next
The city's Water Subcommittee reviewed the proposal June 25 and told staff to move forward, the report says. The developer is seeking grading permits, which allow work to level the land, for the three buildings and a truck trailer parking yard. Grading and the remaining off-site work are expected to begin in November, according to staff.
The commission meets at 6 p.m. Tuesday, Nov. 17, in the Council Chambers at Rialto City Hall, 150 S. Palm Ave.