Fontana studio set faces $47,858 in added costs after aborted install trip, pending council vote
Fontana's City Council is scheduled Nov. 24 to vote on adding $47,858.24 to a contract for its FXN Studio sets, covering an aborted install trip, six months of storage, and a new crew.

What to know
- Fontana's council votes Nov. 24 on adding $47,858.24 to a contract for designing and installing its FXN Studio sets.
- The change would raise the contract to $527,597.15 and covers an aborted install trip, storage, and a new crew.
- Installation is now set for January 2027. The record does not explain the delay or name the funding source.
Fontana would pay $47,858.24 more to the Denver firm designing and installing sets for its Fontana Experience Network studio if the City Council approves a contract change on Nov. 24. The extra money covers a canceled installation trip, months of storage, and a new install crew.
The change would raise the firm's contract from $479,738.91 to $527,597.15. That is an increase of about 10%, based on the figures in the change order.
The bill comes from Devlin Design Group, LLC, and lists the studio, known as FXN Studio, at 17001 Upland Ave. The change order shows the project has slipped. It lists a revised installation date of January 2027.
What the money covers
Part of the bill pays for a trip that did not go as planned. The change order lists extra days, hotel, meal allowances, and changed flights for installers on what it calls an "Aborted Install Trip." Those four charges total $4,826.04.
The firm also wants $1,362.20 for metal framing bought at Home Depot. The change order says the material was for a structural workaround to the ceiling grid that the city requested.
Another large piece is storage. The firm would charge $5,760 to store the studio's set pieces for six months, based on the new January date. The change order lists the months as June through December.
The rest covers people's time and travel. The firm bills for phone calls, emails, video meetings, and research by its principals, including Dan Devlin, and by its senior project manager. It also bills for hours it expects to add. A separate set of charges pays an installation crew, with travel, a rental van, hotel, and meal allowances, for a December install.
The firm also adds a $900 administrative fee. The change order says the fee pays for tracking the delay costs and preparing the estimate and bill.
What the record does not say
The agenda materials include only the firm's change order. They do not include a city staff report.
The record does not say why the earlier installation trip was called off, or who was responsible for the delay. It does not say where the money would come from in the city budget. It also does not explain what the studio will be used for or when it is expected to open.
The dates in the change order also do not fully match. The crew charges are labeled for a December install, while the storage line points to a January 2027 install date.
The change order is numbered 06, which suggests earlier changes to the contract. The city's records show no earlier council actions on this item, and the agenda does not list the earlier changes or their costs.
How the vote works
The item is on the consent calendar, a list of routine items approved together in one vote, without discussion. Any council member can ask to pull an item for a separate discussion and vote.
The same consent calendar includes the final vote on smaller building setbacks in the Gateway area. According to the Gazette's Votes Logged tracker, the Fontana City Council had recorded 36 actions at 13 meetings in 2026, as of its Nov. 10 meeting. The tracker lists six council roll calls this year that were not unanimous. In each one, council member Jesus Sandoval voted no.
The change order says its terms are prepaid, due when the city receives the invoice. It becomes part of the existing contract once the city signs it.
What comes next
The council meets at 2 p.m. Tuesday, Nov. 24, at the Steelworkers' Auditorium, 8437 Sierra Ave. The contract change is item N on the agenda.
If the council approves it, the next marker is the installation itself, now set for January 2027. The record does not say whether the firm expects more charges if the date slips again.